Santa Cruz, CA
Cost Consulting
Owner: U.C. Santa Cruz
Architect: U.C. Santa Cruz Physical Planning and Construction
Construction Value: $156,000
Project Size: 1,020 SF
This project is new Electronic Vehicle (EV) Charging Stations at the existing Core West Parking Structure, including removal and replacement of existing transformers and panelboards, addition of a new second transformer and connection to existing electrical systems as well as patch and repair of adjacent paving and concrete.
Go back: Cost Consulting